The first reaction to “delivery within 4 years” is usually: why so long? The short answer: that is exactly why the villa arrives as a real villa. This guide breaks the four years down, year by year — with the signs that let you track a project’s pace yourself.
Before year one even starts: the paperwork
A serious project starts before sales, not after: owned land, ministerial decree, building licence. This stage never appears in ads, but it is the difference between a project and a gamble — which is why, in our projects, the decree and licence precede the sales opening, never chase it.
Year one: below the ground
Excavation, foundations, basements and the main infrastructure networks. Visually the slowest year — you pass by and it “still looks like land” — but structurally the most important: every mistake here surfaces later above ground.
Year two: the structure rises
Concrete skeletons, columns and slabs, floor after floor. This is the year progress becomes visible and percentages jump. A live example from our own sites: Moon Hills 4 is at 50% construction with sales running in parallel.
Year three: finishing and utilities
External finishes, internal utility networks, landscaping taking shape. Another live example: Moon Hills 3 is at 85% construction — the stage where a construction site turns into a compound.
Year four: handover
Final finishes, utility testing, unit-by-unit handovers. This is where a developer’s record shows: we have delivered two complete projects in Green October — walk through Moon Hills 2 yourself and judge the record with your own eyes.
How to track a project’s pace yourself
- Visit every 4–6 months: real progress is visible — compare against your last visit.
- Ask for the construction percentage as a number: a developer that publishes its figures (like our 85% and 50%) is not afraid of the question.
- Look at the developer’s older projects: whoever delivered before in the same district will likely deliver again.
And if you are entering a pre-launch project like Moon Hills 6 (delivery within 4 years): understand the EOI system first — those four years are exactly what makes your entry price today different from the handover price.
Want to see projects at every stage of this timeline in person? Hotline 15571 · WhatsApp +20 113 231 8097.